New Plant Construction
Original Geographic Overview of New Plant Area of Fujian Refining and Ethylene Project (taken on May 16th, 2004)
Site Preparation of New Plant Area of Fujian Refining and Ethylene Project (taken on April 25th, 2005)
Construction Overview of New Plant Area (taken on April 29, 2007)
Construction Overview of New Plant Area
Pile Foundation Works of APS/VPS, Hydrogenation, Aromatics Complex and PE Units commenced on May 31st, 2006.
800 KTPA Ethylene Cracking Unit of Fujian Refining and Ethylene Project commenced on November 8th, 2006.
On December 21st, 2006, construction of Aromatics Complex commenced.
Aromatics Complex under Construction (taken on December 27th, 2007)
Ethylene Unit under Construction (taken on August 28th, 2008)
Transportation of Quench Water Column of Steam Cracking(taken on February 19th, 2008)
Qinglanshan Terminal Construction
Previous Qinglanshan Crude Terminal landscape
site leveling
On April 29th, 2006, QLS 300,000 DWT Crude Oil Terminal Project commenced
Qinglanshan Terminal under Construction (taken on November 19th, 2006)
Qinglanshan Terminal under Construction (taken on July 9th, 2007)
Qinglanshan 300,000 DWT Crude Oil
Opening Ceremony of Qinglanshan 300,000 DWT Crude Oil Terminal Held
On February 15th, 2009, the first 300,000DWT Oil Tanker successfully berthed at Qinglanshan Terminal for loading/unloading.